고속철도사업의 비용분석 사례

An Introduction to Cost Analysis of Korea High-Speed Railway Project

초록

In this study, we have analyzed the cost of korea high-speed railway system. The predicted cost in planning phase and adjustment data to 5th year are collected. Then, predicted cost is compared with adjustment in year/item/system base. We make a project history table for criteria to review project history and research & development activity. We have developed CBS(cost breakdown structure) and allocated adjustment data to them. It is shown that cost prediction related to research & development activity in planning phase is relatively correct.

제목
고속철도사업의 비용분석 사례
제목 (타언어)
An Introduction to Cost Analysis of Korea High-Speed Railway Project
저자
이태형; 박춘수; 박찬경
발행일
2005-12-06
학회명
2005 국방비용분석세미나