Purpose *Power consumption and load pattern analysis on DC urban transit system *Peak load management - AC Load : General Electric (Light, Air conditioning, Signal facility and Etc.) - DC Load : DC Electric Multiple Unit *Monitoring system - Substation : 22.9kV high voltage monitoring ( 22.9kv KEPCO receiving end 22.9kV catenary) - Electric room : High voltage & Low voltage monitoring (6.6kV , 380V) ??This paper?K *Shows that each electricity power consumption monitoring of facilities *Show that each load pattern analysis of facilities Introduction
- 제목
- Installation of power monitoring system for load pattern analysis on DC Urban Transit system
- 저자
- 정호성; 김형철; 신승권; 윤기용; 김재문; 김양수
- 발행일
- 2013-07-01
- 학회명
- ISGC&E